... | ... | @@ -29,6 +29,10 @@ This is the current picture of the items in the sprint: |
|
|
| | **Total Unplanned** | **2** | 2 |
|
|
|
| | **Total** | **40** | 12 |
|
|
|
|
|
|
UPDATE 10/09/2018: With one week into the sprint no story has been completed and closed.
|
|
|
**UPDATE 10/09/2018**: With one week into the sprint no story has been completed and closed.
|
|
|
|
|
|
UPDATE 20/09/2018: With one week to go, around 1/4 of the planned work to be done has been completed. |
|
|
\ No newline at end of file |
|
|
**UPDATE 20/09/2018**: With one week to go, around 1/4 of the planned work to be done has been completed.
|
|
|
|
|
|
**UPDATE 11/10/2018**: The sprint time-box finished but there wasn't Sprint Review or Retrospective due to other commitments. The following week these two events didn't take place. No Sprint Planning either.
|
|
|
|
|
|
The idea now is to restart Sprints in November, however since the summer commitment to sprints has been erratic at best. Missing staff, pressures before the long shutdown and lack of interest are slowly killing Scrum for BLISS (if not already a zombie) |
|
|
\ No newline at end of file |