... | ... | @@ -29,8 +29,9 @@ This is the current picture of the items in the sprint: |
|
|
| U 18/05 | #350 Acquisition Master "external" channels | 2 | DONE 22/05 |
|
|
|
| U 29/05 | #362 Tests in ID10 | 1 | DONE 01/06 |
|
|
|
| U 29/05 | #363 Scatter plot | 2 | DONE 01/06 |
|
|
|
| U 06/06 | #378 Initialize hardware | 2 | |
|
|
|
| | **Total Planned** | 46 | 19 |
|
|
|
| | **Total Unplanned** | 11 | 11 |
|
|
|
| | **Total Unplanned** | 13 | 11 |
|
|
|
| | **Grand Total** | **54** | **30** |
|
|
|
|
|
|
Please note that issue #329 (5pts) was split during the sprint in three different issues:
|
... | ... | |