... | ... | @@ -24,9 +24,10 @@ This is the current picture of the items in the sprint: |
|
|
| *U* | *#269 Wago with proxy* | | *Added just after sprint planning* |
|
|
|
| U 15/05 | #297 Flex counters integration | 5 | DONE 17/05 |
|
|
|
| U 16/05 | #340 No more wsgi | 1 | DONE 17/05 |
|
|
|
| U 18/05 | #350 Acquisition Master "external" channels | 2 | DONE 22/05 |
|
|
|
| | **Total Planned** | 46 | 5 |
|
|
|
| | **Total Unplanned** | 6 | 6 |
|
|
|
| | **Grand Total** | **52** | **11** |
|
|
|
| | **Total Unplanned** | 8 | 8 |
|
|
|
| | **Grand Total** | **54** | **13** |
|
|
|
|
|
|
At the end of the first week (1/4 of the sprint length) we have completed 11pts, which is roughly the desired speed, however only 5 of these 11pts were for stories planned for the sprint:
|
|
|
|
... | ... | |