... | ... | @@ -38,11 +38,13 @@ Please note that issue #329 (5pts) was split during the sprint in three differen |
|
|
* #357
|
|
|
* #358
|
|
|
|
|
|
At the end of the first week (1/4 of the sprint length) we have completed 11pts, which is roughly the desired speed, however only 5 of these 11pts were for stories planned for the sprint:
|
|
|
By the end of the third week the team was completing stories at the desired speed, however unplanned items were a significant proportion of all items and some planned items won't be completed by the end of the sprint. In particular, the kmap expriement scheduled for 2nd of June had to be done using SPEC, not BLISS.
|
|
|
|
|
|
![image](/uploads/86d98789973e074fa562cf8f773c7f12/image.png)
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Time spent on non-BLISS tasks:
|
|
|
|
|
|
| Team Member | week 1 | week 2 | week 3 | week 4 | **Average** |
|
... | ... | |