... | ... | @@ -9,10 +9,12 @@ This is the current picture of the items in the sprint: |
|
|
| C | #293 New time correlator device: FLEX | 1 left | DONE 17/05 |
|
|
|
| 1 | #336 ID13 kmap experiment preparation | 0 | *Roberto to do so* |
|
|
|
| 1 | #334 ID13 kmap scan | 8 | |
|
|
|
| 1 | #329 Trajectory support PI-E712 | 5 | DONE 28/05 |
|
|
|
| 1 | #333 MAXIPIX camera integration | 2 | DONE 28/05 |
|
|
|
| 1 | #335 Eiger camera integration | 2 | DONE 28/05 |
|
|
|
| 1 | #337 Documentation: motion control | 5 | |
|
|
|
| 1 | #329 Trajectory support PI-E712 | 5 | DONE 28/05 *modified to 2pts* |
|
|
|
| 1b | #357 Trajectory: add support for patterns | | *split up from #329* |
|
|
|
| 1b | #358 PI-E712: use pattern API for trajectory | | *split up from #329* |
|
|
|
| 2 | #330 New PI M850 hexapod motor controller | 5 | |
|
|
|
| 2 | #332 Check NEWPORT XPS controller | 1 | |
|
|
|
| 2 | #331 New SMARACT piezo motor controller | 3 | DONE 30/05 |
|
... | ... | @@ -25,9 +27,15 @@ This is the current picture of the items in the sprint: |
|
|
| U 15/05 | #297 Flex counters integration | 5 | DONE 17/05 |
|
|
|
| U 16/05 | #340 No more wsgi | 1 | DONE 17/05 |
|
|
|
| U 18/05 | #350 Acquisition Master "external" channels | 2 | DONE 22/05 |
|
|
|
| | **Total Planned** | 46 | 17 |
|
|
|
| | **Total Unplanned** | 8 | 8 |
|
|
|
| | **Grand Total** | **54** | **25** |
|
|
|
| U 29/05 | #363 Scatter plot | 2 | DONE 01/06 |
|
|
|
| | **Total Planned** | 46 | 14 |
|
|
|
| | **Total Unplanned** | 10 | 10 |
|
|
|
| | **Grand Total** | **54** | **24** |
|
|
|
|
|
|
Please note that issue #329 (5pts) was split during the sprint in three different issues:
|
|
|
* #329 revalued to 2 points
|
|
|
* #357
|
|
|
* #358
|
|
|
|
|
|
At the end of the first week (1/4 of the sprint length) we have completed 11pts, which is roughly the desired speed, however only 5 of these 11pts were for stories planned for the sprint:
|
|
|
|
... | ... | |