... | ... | @@ -24,11 +24,11 @@ This is the current picture of the items in the sprint: |
|
|
| *U* | *#269 Wago with proxy* | | *Added just after sprint planning* |
|
|
|
| U 15/05 | #297 Flex counters integration | 5 | DONE 17/05 |
|
|
|
| U 16/05 | #340 No more wsgi | 1 | DONE 17/05 |
|
|
|
| | **Total Planned** | 46 | 4 |
|
|
|
| | **Total Planned** | 46 | 5 |
|
|
|
| | **Total Unplanned** | 6 | 6 |
|
|
|
| | **Grand Total** | **52** | **10** |
|
|
|
| | **Grand Total** | **52** | **11** |
|
|
|
|
|
|
At the end of the first week (1/4 of the sprint length) we have completed 10pts, which is roughly the desired speed, however only 4 of these 10pts were for stories planned for the sprint:
|
|
|
At the end of the first week (1/4 of the sprint length) we have completed 11pts, which is roughly the desired speed, however only 5 of these 11pts were for stories planned for the sprint:
|
|
|
|
|
|
![image](/uploads/7c79eb9501c71ef346b184f3de0e8688/image.png)
|
|
|
|
... | ... | |