... | ... | @@ -29,19 +29,34 @@ This is the current picture of the items in the sprint: |
|
|
| | **Total Unplanned** | **20+** | 20 |
|
|
|
| | **Grand Total** | **59+** | 40 |
|
|
|
|
|
|
Waiting list of Items *Pending integration*:
|
|
|
* #276 id11 Piezo Scan
|
|
|
|
|
|
|
|
|
Time spent on non-BLISS tasks:
|
|
|
|
|
|
| Team Member | week 1 | week 2 | week 3 | **Average** |
|
|
|
|-------------|----------|----------|----------|-------------|
|
|
|
| S. Petitdemange | - | % | % | **%** |
|
|
|
| T. Coutinho | 70% | % | % | **%** |
|
|
|
| C. Guilloud | - | % | % | **%** |
|
|
|
| V. Michel | 10% | % | % | **%** |
|
|
|
| M. Guijarro | 20% | 0% | % | **%** |
|
|
|
| E. Papillon | - | % | % | **%** |
|
|
|
| Average non-BLISS | % | % | % | **%** |
|
|
|
| Total non-BLISS | % FTE | % FTE | % FTE | **% FTE** |
|
|
|
|
|
|
![image](/uploads/4e758f37c97f55c83259c06ff78ae629/image.png)
|
|
|
|
|
|
![image](/uploads/560cc6338ee1595d0000e3f665dfc37c/image.png) |
|
|
| S. Petitdemange | - | 80% | 50% | **65%** |
|
|
|
| T. Coutinho | 70% | - | - | **70%** |
|
|
|
| C. Guilloud | - | 75% | - | **75%** |
|
|
|
| V. Michel | 10% | 10% | 15% | **12%** |
|
|
|
| M. Guijarro | 20% | 0% | 30% | **17%** |
|
|
|
| E. Papillon | - | 100% | - | **100%** |
|
|
|
| Average non-BLISS | 33% | 53% | 32% | **39%** |
|
|
|
| Total non-BLISS | 100% FTE | 265% FTE | 95% FTE | **153% FTE** |
|
|
|
|
|
|
The burndown charts below show that we started very well and if it wouldn't have been for all the *unplanned* items that we added we could have completed all items in the sprint.
|
|
|
|
|
|
![image](/uploads/6cd43724d75ca9214b08740beb2cb80e/image.png)
|
|
|
|
|
|
![image](/uploads/2f06f54c32cb4c8e040645dea3d76319/image.png)
|
|
|
|
|
|
The team agreed that next week is not suitable for sprinting (with most of the team on leave and bank holidays Tuesday and Thursday), therefore the next Sprint Planning meeting will be 14/05/2018
|
|
|
|
|
|
Also, the items currently in Development will be put on hold during next sprint:
|
|
|
* #290 3-leg table calc. motor
|
|
|
* #296 Help getting started with BLISS
|
|
|
* #294 Meerstetter new temp cont
|
|
|
* #293 New time correlator device: FLEX
|
|
|
|