... | ... | @@ -42,7 +42,13 @@ Availability: |
|
|
| M. Guijarro | 20% | 10% | 10% | **13%** |
|
|
|
| E. Papillon | 70% | 20% | 70% | **53%** |
|
|
|
| Average non-BLISS | 41% | 23% | 42% | **35%** |
|
|
|
| Total non-BLISS | 245% FTE | 135% FTE | 350% FTE | **209% FTE** |
|
|
|
| Total non-BLISS | 245% FTE | 135% FTE | 250% FTE | **209% FTE** |
|
|
|
|
|
|
And this is the burn down chart:
|
|
|
|
|
|
![image](/uploads/acaa15ad214026d99c4bff09f0eda5dd/image.png)
|
|
|
|
|
|
![image](/uploads/aedef5cb86ff4688443a70e83c4f0601/image.png)
|
|
|
|
|
|
As we can see,
|
|
|
- We completed 29 points of the 53 planned (the rest were unplanned): 55%
|
... | ... | @@ -50,7 +56,11 @@ As we can see, |
|
|
- We added 15 unplanned points, increasing the total number of points on the sprint by 28%
|
|
|
- We completed nearly all the unplanned items: 4out of 5 items and 14 out of 15 points 93%
|
|
|
- We manage to deliver a total 45 points out of a total of 68: 66%
|
|
|
- We estimated to have spent around 58% of the working time on BLISS (excluding BLISS commissioning)
|
|
|
|
|
|
And we are progressing well in terms of:
|
|
|
1. Time spent on BLISS (team members are focusing more of their time in the project)
|
|
|
2. Planned work completed (we are getting better at estimating what we can do during a sprint)
|
|
|
|
|
|
|
|
|
And this is the burn down chart:
|
|
|
|
|
|
![image](/uploads/acaa15ad214026d99c4bff09f0eda5dd/image.png) |
|
|