... | ... | @@ -53,7 +53,7 @@ And this is the burn down chart: |
|
|
As we can see,
|
|
|
- We completed 29 points of the 53 planned (the rest were unplanned): 55%
|
|
|
- If we consider _#249 Spect motor controller_ in the place of planned item de-prioritised we get up to 31/53: 58%
|
|
|
- We added 15 unplanned points, increasing the total number of points on the sprint by 28%
|
|
|
- We added 15 unplanned points, increasing the total number of points in the sprint by 28%
|
|
|
- We completed nearly all the unplanned items: 4out of 5 items and 14 out of 15 points 93%
|
|
|
- We manage to deliver a total 45 points out of a total of 68: 66%
|
|
|
- We estimated to have spent around 58% of the working time on BLISS (excluding BLISS commissioning)
|
... | ... | |