6th Sprint Follow up
|
|
|
---------------------
|
|
|
6th Sprint Follow up & Retrospective
|
|
|
------------------------------------
|
|
|
|
|
|
This is the current picture of the items in the sprint:
|
|
|
|
... | ... | @@ -26,14 +26,10 @@ This is the current picture of the items in the sprint: |
|
|
| U 29/01 | #232 Silx and BLISS meeting | 3 | 30/01 |
|
|
|
| | **Total** | **46** | 12 |
|
|
|
| | **Unplanned Total** | **22** | 22 |
|
|
|
| | **Grand Total** | **65** | 34 |
|
|
|
| | **Grand Total** | **68** | 34 |
|
|
|
|
|
|
Also, #144 MCA Scans worth 3 points was done, but not identified at the beginning of the sprint as a continuation item.
|
|
|
|
|
|
These are the burn down chart:
|
|
|
![image](/uploads/4ce53d0ec0fe71392c91968683ab1343/image.png)
|
|
|
|
|
|
|
|
|
And this is a rough estimation of the time spent on non-BLISS items:
|
|
|
|
|
|
| Team Member | week 1 | week 2 | week 3 | week 4 | **Average** |
|
... | ... | @@ -44,4 +40,27 @@ And this is a rough estimation of the time spent on non-BLISS items: |
|
|
| V. Michel | 0% | 33% | 15% | | **%** |
|
|
|
| M. Guijarro | 20% | 20% | 40% | 40% | **%** |
|
|
|
| Average non-BLISS | 35% | 39% | 52% | 50% | **44%** |
|
|
|
| Total non-BLISS | 175% FTE | 193% FTE | 260% FTE | 200% FTE | **207%** | |
|
|
\ No newline at end of file |
|
|
| Total non-BLISS | 175% FTE | 193% FTE | 260% FTE | 200% FTE | **207%** |
|
|
|
|
|
|
As we can see,
|
|
|
* We completed 12 points of the 46 planned (the rest were unplanned): 26%
|
|
|
* If we consider *#144 MCA Scans* and *#227 Trajectory investigation* in the place of planned items de-prioritised we get up to 23/46: 50%
|
|
|
* We added 22 unplanned points, increasing the total number of points on the sprint by 48%
|
|
|
* We completed all the unplanned items: 100%
|
|
|
* We manage to deliver a total 34 points out of a total of 68: 50%
|
|
|
* We almost completed *#219 PEPU Integration* and *#215 Basic Training and doc*
|
|
|
|
|
|
These are the burn down chart:
|
|
|
![image](/uploads/4ce53d0ec0fe71392c91968683ab1343/image.png)
|
|
|
|
|
|
During the **retrospective** we raised the following points:
|
|
|
1. Morning's stand ups: consider twice a week instead of three times. Cosider also doing them 15min later to ensure good attendance.
|
|
|
2. We will continue with 4 week long sprints for now
|
|
|
3. We will continue DCM work next sprint to try to finish all items listed above
|
|
|
4. Task breakdowns are useful, we should try to be more precise in this area
|
|
|
5. Upon completion of a task we will quickly reevaluate the number of points that should have had
|
|
|
6. Unplanned items should be carefully analysed before decide to add them to the sprint.
|
|
|
7. We will study how to centralise helpdesk functions within the Bliss development team to ensure less interruptions.
|
|
|
|
|
|
![image](/uploads/3f7ee5c769c3ca74fc5932d5c941e9be/image.png)
|
|
|
|