6th Sprint Planning - DCM
|
|
|
--------------------------
|
|
|
|
|
|
The 6th Sprint Planning meeting took place 09/01/2018.
|
|
|
|
|
|
**Length of the sprint**: 4 weeks, but starting on Tuesday rather than Monday (09/01 to 02/02)
|
|
|
|
|
|
| **Team Members** | availability |
|
|
|
| -------------------- | --------- |
|
|
|
| S. Petitdemange | ~ 15 days (one week off) |
|
|
|
| T. coutinho | ~ 17 days (two days off) |
|
|
|
| C. Guilloud | ~ 15 days (one week off) |
|
|
|
| V. Michel | ~ 19 days estimated |
|
|
|
| M. Guijarro | ~ 19 days |
|
|
|
| G. Berruyer | Product Owner |
|
|
|
| J. Bodera | Scrum Master |
|
|
|
|Total | **85 days** |
|
|
|
|
|
|
Events:
|
|
|
* **"Daily" Scrum** to take place at 09:30h Mondays, Wednesdays and Fridays for up to 15min
|
|
|
* **Sprint Review (demo)** : Friday 02/02 at 13:30h (1 hour max)
|
|
|
* **Sprint Retrospective**: Friday 02/02after the demo (1 hour max)
|
|
|
* **Next Sprint Planning** Monday 05/02/2018 at 13:30h
|
|
|
|
|
|
**Sprint Backlog** : The team agreed that it should be reasonable to try to complete the following (C means an item that carries over from the last sprint):
|
|
|
|
|
|
|
|
|
| **Priority** | **Story** | **Points** | **Comment** |
|
|
|
| ------------ | --------- | ---------- |------------ |
|
|
|
| C | #194 Discussion about MCA | 3 | |
|
|
|
| C | #177 Scan info | 3 | |
|
|
|
| 1 | #211 Environment installation| 3 | |
|
|
|
| 2 | #215 Basic Bliss training and doc | 13 | |
|
|
|
| 3 | #216 Calculation motor fix | ? | *To evaluate* |
|
|
|
| 4 | #217 Continuous scan | 5 | |
|
|
|
| 5 | #218 Trajectory discussion | 3 | |
|
|
|
| 6 | #219 PEPU Integration | 5 | |
|
|
|
| 7 | #220 Energy Calculation | 3 | |
|
|
|
| 8 | #221 PEL Integration | | 3 |
|
|
|
| 9 | #222 Speedgoat discussion | 5 | |
|
|
|
| | **Total** | **46** | *A few more when the bug evaluated* |
|
|
|
|
|
|
During the last sprints we managed 34, 36 and 43 points to be completed, so 46 seems reasonable. We do have four days extra this time, so in case we are advancing faster than expected we will ask Gilles to create some more user stories for the ~DCM
|
|
|
|
|
|
We didn't do a Sprint Review neither Retrospective the last time, so it is important that we do them at the end of this sprint. |
|
|