... | ... | @@ -36,6 +36,7 @@ The final picture of the sprint backlog is: |
|
|
| | **Grand Total** | **63** | **43** |
|
|
|
|
|
|
Team availability:
|
|
|
|
|
|
| Team Member | week 1 | week 2 | week 3 | **Average** |
|
|
|
|-------------|----------|----------|----------|-------------|
|
|
|
| S. Petitdemange | 20% | 20% | 20% | **20%** |
|
... | ... | @@ -51,7 +52,7 @@ As we can see, |
|
|
* We completed 29 points of the 49 planned (the rest were unplanned): 59%
|
|
|
* We added 14 unplanned points, increasing the total number of points on the sprint by 29%
|
|
|
* We completed all the unplanned items: 100%
|
|
|
* we manage to deliver a total 43 points out of 49 we wanted to do: 88%
|
|
|
* we manage to deliver a total 43 points out of a total of 63: 68%
|
|
|
![image](/uploads/f9267141fcca83dd45b75692cd6feba5/image.png)
|
|
|
* It looks like we are getting better at estimating as we complete a higher percentage of the planned work
|
|
|
* Time spent on BLISS went down due to other projects rushed in before the end of the year
|
... | ... | |