End of 5th Sprint
|
|
|
------------------
|
|
|
|
|
|
The 5th sprint took place from 04/12/2017 to 21/12/2017 (nearly 3 weeks).
|
|
|
|
|
|
The **sprint review and retrospective didn't take place** on Friday 21st December as planned because the team decided so based on:
|
|
|
1. Significant amount of missing staff members
|
|
|
2. Willingness of developers to finish items nearly completed before the winter break
|
|
|
|
|
|
The final picture of the sprint backlog is:
|
|
|
This is the current picture of the items in the sprint:
|
|
|
|
|
|
| **Priority** | **Story** | **Points** | **Completed** |
|
|
|
| ------------ | --------- | ---------- |-------------- |
|
|
|
| *C*| *#105 Kb Focus* | *2* | *Only if beam time available* |
|
|
|
| C | #192 Review and add final tests | 5 | |
|
|
|
| C | #132 motor symhexa v1 | 3 | |
|
|
|
| C | #133 motor pi e712 | 5 | 14/12/2017 |
|
|
|
| C | #174 hardware init discussion | 3 | |
|
|
|
| C | #177 Scan info dictionary & watch session scans | 3 | |
|
|
|
| | #191 Vaisala humidity and temp sensor| 3 | 08/12/2017 |
|
|
|
| | #161 Handle multiple P201 cards | 5 | 21/12/2017 |
|
|
|
| | #193 BLISS Strategy document | 8 | 19/12/2017 |
|
|
|
| | #188 Session Refactoring | 8 | 11/12/2017 |
|
|
|
| | #144 MCA Scans | 3 | *Only testing* |
|
|
|
| | #194 Discussion about MCA counters | 3 | |
|
|
|
| U 07/12/2017 | #196 Add temperature devices to Bliss tango server | 2 | 07/12/2017 |
|
|
|
| U 07/12/2017 | #197 Bliss tango server is broken in master | 1 | 07/12/2017 |
|
|
|
| U 11/12/2017 | #198, #200, #201 & #202 | 4 (1 each) | 12/12/2017 |
|
|
|
| U 12/12/2017 | #203 Mock up controller | 1| 19/12/2017 |
|
|
|
| U 12/12/2017 | #204 motion.mac | 1 | 19/12/2017 |
|
|
|
| U 14/12/2017 | #205 load script nameplace problem | 2 | 19/12/2017 |
|
|
|
| U 20/12/2017 | #206 bliss session documentation | 2 | 20/12/2017 |
|
|
|
| U 20/12/2017 | #207 X,Y axes on top of [...] motor | 1 | 20/12/2017 |
|
|
|
| | **Total** | **49** | 29 |
|
|
|
| | **Unplanned Total** | **14** | 14 |
|
|
|
| | **Grand Total** | **63** | **43** |
|
|
|
|
|
|
Team availability:
|
|
|
|
|
|
| Team Member | week 1 | week 2 | week 3 | **Average** |
|
|
|
|-------------|----------|----------|----------|-------------|
|
|
|
| S. Petitdemange | 20% | 20% | 20% | **20%** |
|
|
|
| T. coutinho | 20% | 30% | --- | **25%** |
|
|
|
| C. Guilloud | 75% | 80% | 80% | **78%** |
|
|
|
| V. Michel | --- | 80% | 80% | **80%** |
|
|
|
| M. Guijarro | 20% | 20% | | **20%** |
|
|
|
| E. Papillon | 100% |100% | | **100%** |
|
|
|
| Average non-BLISS | 47% | 55% | 60% | **54%** |
|
|
|
| Total non-BLISS | 2.35 FTE | 3.30 FTE | 3.00 FTE | **2.88 FTE** |
|
|
|
|
|
|
And the burn-down charts:
|
|
|
![image](/uploads/c627508b3aabe0dd88b315d93b57589c/image.png)
|
|
|
![image](/uploads/c94386696f073c2419e9c14d5992908a/image.png) |
|
|
\ No newline at end of file |