... | ... | @@ -8,7 +8,6 @@ The **sprint review and retrospective didn't take place** on Friday 21st Decembe |
|
|
2. Willingness of developers to finish items nearly completed before the winter break
|
|
|
|
|
|
The final picture of the sprint backlog is:
|
|
|
This is the current picture of the items in the sprint:
|
|
|
|
|
|
| **Priority** | **Story** | **Points** | **Completed** |
|
|
|
| ------------ | --------- | ---------- |-------------- |
|
... | ... | @@ -37,7 +36,6 @@ This is the current picture of the items in the sprint: |
|
|
| | **Grand Total** | **63** | **43** |
|
|
|
|
|
|
Team availability:
|
|
|
|
|
|
| Team Member | week 1 | week 2 | week 3 | **Average** |
|
|
|
|-------------|----------|----------|----------|-------------|
|
|
|
| S. Petitdemange | 20% | 20% | 20% | **20%** |
|
... | ... | @@ -49,6 +47,15 @@ Team availability: |
|
|
| Average non-BLISS | 47% | 55% | 60% | **54%** |
|
|
|
| Total non-BLISS | 2.35 FTE | 3.30 FTE | 3.00 FTE | **2.88 FTE** |
|
|
|
|
|
|
And the burn-down charts:
|
|
|
As we can see,
|
|
|
* We completed 29 points of the 49 planned (the rest were unplanned): 59%
|
|
|
* We added 14 unplanned points, increasing the total number of points on the sprint by 29%
|
|
|
* We completed all the unplanned items: 100%
|
|
|
* we manage to deliver a total 43 points out of 49 we wanted to do: 88%
|
|
|
![image](/uploads/f9267141fcca83dd45b75692cd6feba5/image.png)
|
|
|
* It looks like we are getting better at estimating as we complete a higher percentage of the planned work
|
|
|
* Time spent on BLISS went down due to other projects rushed in before the end of the year
|
|
|
|
|
|
And the **burn-down charts**:
|
|
|
![image](/uploads/c627508b3aabe0dd88b315d93b57589c/image.png)
|
|
|
![image](/uploads/c94386696f073c2419e9c14d5992908a/image.png) |
|
|