4th Sprint Planning
|
|
|
---------------------
|
|
|
|
|
|
The 4th Sprint Planning meeting took place 13/11/2017.
|
|
|
|
|
|
**Length of the sprint**: 3 weeks (13/11 to 01/12)
|
|
|
|
|
|
| **List of attendees** | availability |
|
|
|
| -------------------- | --------- |
|
|
|
| S. Petitdemange | 10 days |
|
|
|
| T. coutinho | 15 days |
|
|
|
| C. Guilloud | 10 days |
|
|
|
| V. Michel | 07 days |
|
|
|
| M. Guijarro | 10 days |
|
|
|
| E. Papillon | 10 days |
|
|
|
| J. Bodera | SM |
|
|
|
|Total | **62 days** |
|
|
|
|
|
|
Events:
|
|
|
* **Daily Scrum** to take place at 13:30 every day. Scheduled to last up to 15min. Meeting will stop after 15 minutes even if not finished
|
|
|
* **Sprint Review (demo)** : Friday 01/12 at 13:30h (1 hour max)
|
|
|
* **Sprint Retrospective**: Friday 01/12 after the demo (1 hour max)
|
|
|
* **Next Sprint Planning** Monday 04/121 at 13:30h
|
|
|
|
|
|
Jens Meyer indicated his intention to attend if possible the Sprint Review, Retrospective and next Planning.
|
|
|
|
|
|
**Sprint Backlog** : The team agreed that it should be reasonable to try to complete the following (C means an item that carries over from the last sprint):
|
|
|
|
|
|
| **Priority** | **Story** | **Points** |
|
|
|
| ------------ | --------- | ---------- |
|
|
|
| C | #105 Kb Focus | 5 |
|
|
|
| C | #156 P201 in scans| 13 |
|
|
|
| C | #172 Refactoring data handling| 13 |
|
|
|
| | #140 1D Data handling | 8 |
|
|
|
| | #132 motor symhexa v1 | 3 |
|
|
|
| | #133 motor pi e712 | 5 |
|
|
|
| | #165 Data file not always closed | 2 |
|
|
|
| | #173 MCA: further design specs | 5 |
|
|
|
| | #175 Discussion about "session" | 3 |
|
|
|
| | #174 hardware init discussion | 3 |
|
|
|
| | #177 Scan info dictionary & watch session scans | 3 |
|
|
|
| | **Total** | **58** |
|
|
|
|
|
|
Last sprint we managed 34 points, therefore it looks a bit high, but we have increased the resources available for the sprint.
|
|
|
|
|
|
At the time of writing, the burn down chart looks like:
|
|
|
![image](/uploads/4026166d7b4000d2d21bc58d8d839885/image.png)
|
|
|
|
|
|
The team noted that in the next sprint (5th sprint)
|
|
|
* DCM tasks need to be included. Gilles Berruyer to be the product owner for this.
|
|
|
* lazy_init
|
|
|
* uniformization of set/get methods |
|
|
\ No newline at end of file |