End of 3rd Sprint
|
|
|
------------------
|
|
|
|
|
|
The 3rd sprint took place from 16/10/2017 to 10/11/2017 (4 weeks), including the week of 1st November when many people were on leave.
|
|
|
|
|
|
The final picture of the sprint was:
|
|
|
|
|
|
| **Priority** | **Story** | **Points** | **Completed** |
|
|
|
| ------------ | --------- | ---------- | ------------- |
|
|
|
| | #112 Motor ice linked axis | 5 | 10/11/2017 |
|
|
|
| | #105 Kb Focus | 5 | |
|
|
|
| | #75 Simple P201 config | 8 | 10/11/2017 |
|
|
|
| | #140 1D Data Handling | 8 | |
|
|
|
| | #156 P201 in scans | 13 | |
|
|
|
| | ~~#150 Testing Mercury 4 controller~~ | ~~3~~ | exchanged for item #151 24/10 |
|
|
|
| | #151 Testing the XMAP controller | 3 | 24/10/2017 |
|
|
|
| U 19/10 | #162 ID29 Energy Scan Implementation | 5 | 07/11/2017 |
|
|
|
| U 19/10 | #163 BPM images saving while acquisition | 2 | 31/10/2017 |
|
|
|
| U 19/10 | #164 Summary of tasks for BLISS Roadmap | 3 | 20/10/2017 |
|
|
|
| U 23/10 | #167 ID31 potentiostat scan | 3 | 23/10/2017 |
|
|
|
| U 02/11 | #170 Multiple session objects | 2 | 06/11/2017 |
|
|
|
| U 02/11 | #171 Acquisition Channel objects | 3 | |
|
|
|
| U 02/11 | #172 Type in AcquisitionDevice and AcquisitionChannel | 5 | |
|
|
|
| U 09/11 | #152 Testing the FalconX controller | 3 | 09/11/2017 |
|
|
|
| | **Planned Total** | 42 | 16 |
|
|
|
| | **Unplanned Total** | 26 | 18 |
|
|
|
| | **Grand Total** | **65** | **34** |
|
|
|
|
|
|
As we can see,
|
|
|
* We only completed 16 points of the 42 planned (the rest were unplanned): 38%
|
|
|
* we manage to deliver 34 points out of 42 we wanted to do: 81%
|
|
|
* We added 26 unplanned points, increasing the total number of points on the sprint by 62%
|
|
|
* |
|
|