... | ... | @@ -18,15 +18,19 @@ The current picture is: |
|
|
| U 19/10 | #163 BPM images saving while acquisition | 2 | 31/10/2017 |
|
|
|
| U 19/10 | #164 Summary of tasks for BLISS Roadmap | 3 | 20/10/2017 |
|
|
|
| U 23/10 | #167 ID31 potentiostat scan | 3 | 23/10/2017 |
|
|
|
| U 02/11 | #170 Multiple session objects | 2 | |
|
|
|
| U 02/11 | #171 Acquisition Channel objects | 3 | |
|
|
|
| U 02/11 | #172 Type in AcquisitionDevice and AcquisitionChannel | 5 | |
|
|
|
| | **Planned Total** | 42 | 3 |
|
|
|
| | **Unplanned Total** | 13 | 8 |
|
|
|
| | **Grand Total** | **55** | **11** |
|
|
|
| | **Unplanned Total** | 23 | 8 |
|
|
|
| | **Grand Total** | **65** | **11** |
|
|
|
|
|
|
Please note that
|
|
|
1. three unplanned items (#162, #163, #164) were added 19th of October.
|
|
|
1. three unplanned items (#162, #163, #164) were added 19th of October and three more (#170, #171, #172) on 2nd November
|
|
|
2. Then on 23rd October an unplanned piece of work worth 3 points was done in ID31 (#167), however it will be fully finished in the next sprint (around 2 points remain to be done there).
|
|
|
3. On 24th October item #151 was done instead of #150. The item #151 is unplanned but as it replaces a planned item we are not marking it as unplanned additional work.
|
|
|
|
|
|
|
|
|
And the burn down chart looks like this:
|
|
|
![image](/uploads/673fee8950b84b8b4140ed2e5af10c3e/image.png)
|
|
|
|
... | ... | |