... | ... | @@ -14,7 +14,7 @@ The current picture is: |
|
|
| | #156 P201 in scans | 13 | |
|
|
|
| | ~~#150 Testing Mercury 4 controller~~ | ~~3~~ | exchanged for item #151 24/10 |
|
|
|
| | #151 Testing the XMAP controller | 3 | 24/10/2017 |
|
|
|
| U 19/10 | #162 ID29 Energy Scan Implementation | 5 | |
|
|
|
| U 19/10 | #162 ID29 Energy Scan Implementation | 5 | 07/11/2017 |
|
|
|
| U 19/10 | #163 BPM images saving while acquisition | 2 | 31/10/2017 |
|
|
|
| U 19/10 | #164 Summary of tasks for BLISS Roadmap | 3 | 20/10/2017 |
|
|
|
| U 23/10 | #167 ID31 potentiostat scan | 3 | 23/10/2017 |
|
... | ... | @@ -22,8 +22,8 @@ The current picture is: |
|
|
| U 02/11 | #171 Acquisition Channel objects | 3 | |
|
|
|
| U 02/11 | #172 Type in AcquisitionDevice and AcquisitionChannel | 5 | |
|
|
|
| | **Planned Total** | 42 | 3 |
|
|
|
| | **Unplanned Total** | 23 | 10 |
|
|
|
| | **Grand Total** | **65** | **13** |
|
|
|
| | **Unplanned Total** | 23 | 15 |
|
|
|
| | **Grand Total** | **65** | **18** |
|
|
|
|
|
|
Please note that
|
|
|
1. three unplanned items (#162, #163, #164) were added 19th of October and three more (#170, #171, #172) on 2nd November
|
... | ... | @@ -32,8 +32,8 @@ Please note that |
|
|
|
|
|
|
|
|
And the burn down chart looks like this:
|
|
|
![image](/uploads/821fa06a89cfa39206f2ac4d8c54b9c9/image.png)
|
|
|
![image](/uploads/18a189bff09fbd0d0094f83b98837403/image.png)
|
|
|
|
|
|
|
|
|
However, it is worth pointing that if all the work done in the unplanned items would have been done instead on planned items the burn down chart would look a lot better:
|
|
|
![image](/uploads/484b40188a7ed7917df0e36e382c55e2/image.png) |
|
|
![image](/uploads/a2393586c9c0655450d459cab883785c/image.png) |