3rd Sprint Planning
|
|
|
---------------------
|
|
|
|
|
|
The 3rd Sprint Planning meeting took place 16/10/2017 at 10:15.
|
|
|
|
|
|
**Length of the sprint**: 4 weeks (16/10 to 10/11)
|
|
|
|
|
|
| **List of attendees** | Unavailability | Total availability |
|
|
|
| -------------------- | ------------ | --------- |
|
|
|
| S. Petitdemange | around 10 days | 9 days |
|
|
|
| T. coutinho | around 4 days | 15 days |
|
|
|
| C. Guilloud | around 3 days | 16 days |
|
|
|
| V. Michel | around 3 days | 16 days |
|
|
|
| M. Guijarro | around 5 days | 14 days |
|
|
|
| E. Papillon | PO: around 6 days | 13 days |
|
|
|
| J. Bodera | SM: around 3 days | 16 days |
|
|
|
|Total | | **70 days** |
|
|
|
|
|
|
During the sprint we have one national holiday (1st November), so the total availability will be around 70 days of work. As usual, we expect significant impact from unexpected work and non-BLISS items.
|
|
|
|
|
|
Events:
|
|
|
* **Daily Scrum** to take place at 09:45 every day. Scheduled to last up to 15min. Meeting will stop after 15 minutes even if not finished
|
|
|
* **Sprint Demo** : Friday 10/11 at 13:00h (Jordi will be absent)
|
|
|
* **Sprint Retrospective**: Friday 10/11 after the demo (around 14:00h)
|
|
|
* **Next Sprint planning** To be confirmed, scheduled for Monday 13/11 at 09:45h for now
|
|
|
|
|
|
During the [last sprint](bliss_scrum_20170929) we failed to complete all the items, so Jordi called for caution when creating the Sprint Backlog, to ensure it is feasible.
|
|
|
|
|
|
**Sprint Backlog** : The team agreed that it should be reasonable to try to complete the following:
|
|
|
|
|
|
| **Priority** | **Story** | **Points** |
|
|
|
| ------------ | --------- | ---------- |
|
|
|
| | #112 Motor ice linked axis | 5 |
|
|
|
| | #105 Kb Focus | 5 |
|
|
|
| | #75 Simple P201 config | 8 |
|
|
|
| | #140 1D Data Handling | 8 |
|
|
|
| | #156 P201 in scans| 13 |
|
|
|
| | #150 Testing Mercury 4 controller | 3 |
|
|
|
| | **Total** | **42** |
|
|
|
|
|
|
![image](/uploads/b86b41a5fd36806db8cc6df8720839f8/image.png)
|
|
|
|
|
|
The Sprint Backlog therefore contains 6 stories adding up 42 points |
|
|