End of 2nd Sprint
|
|
|
------------------
|
|
|
|
|
|
The 2nd Sprint lasted three weeks as planned (starting on Monday 11th September) and the Sprint Review and Sprint Retrospective took place on the 3rd Friday of the sprint (Friday 29th September)
|
|
|
|
|
|
Not all the items planned for the sprint could be completed:
|
|
|
![image](/uploads/7632e031ed84d6971cae46d7a47f7cdd/image.png)
|
|
|
|
|
|
(Please note that one item not scheduled for the sprint and worth 5 points was also completed and not showed in the burn down chart).
|
|
|
|
|
|
Emmanuel Papillon and Jordi Bodera couldn't attend the Retrospective.
|
|
|
|
|
|
These were the main points of the retrospective:
|
|
|
1. We overestimate the time available for BLISS work in the sprint and at the same time we might be underestimating the size of the stories in the sprints. Left over work from before we started the sprints eventually will dry up and we aim to get better at estimating.
|
|
|
2. We like the idea of public regular BLISS sessions on what has been done and what to focus on next every few sprints.
|
|
|
3. We will formalise a plan for obtaining a road map for BLISS in 2018, however at the moment there is enough work for the rest of the year.
|
|
|
4. We may try out something in the daily sprint to make it more lively. Currently we do not have users attending the Sprint Demo and our Product Owner is a proxy for the real users, so we could shift demos into daily scrum. |
|
|