1st Sprint Planning
|
|
|
---------------------
|
|
|
|
|
|
The 2nd Sprint Planning meeting took place 11/09/2017 at 09:45 as planned.
|
|
|
|
|
|
**Length of the sprint**: 3 weeks (11/09 to 29/09)
|
|
|
|
|
|
| **List of attendees** | Availability | Total |
|
|
|
| -------------------- | ------------ | --------- |
|
|
|
| S. Petitdemange | 14 days at 65% | 9 days |
|
|
|
| T. coutinho | 14 days at 70% | 10 days |
|
|
|
| C. Guilloud | 13 days at 70% | 9 days |
|
|
|
| V. Michel | 13 days at 75% | 10 days |
|
|
|
| M. Guijarro | 14 days at 65% | 9 days |
|
|
|
| E. Papillon | Product Owner role | 2 days |
|
|
|
| J. Bodera | Scrum Master role | 2 days |
|
|
|
|Total | | **47 days** |
|
|
|
|
|
|
So approximately we estimated that we will have around 47 days of available time for this sprint.
|
|
|
|
|
|
|
|
|
Events:
|
|
|
* **Daily Scrum** to take place at 09:45 every day. Scheduled to last up to 15min. Meeting will stop after 15 minutes even if not finished
|
|
|
* **Sprint Demo** : Friday 29/09 at 13:00h
|
|
|
* **Sprint Retrospective**: Friday 29/09 after the demo (around 14:00h)
|
|
|
* **Next Sprint planning** scheduled for Monday 02/10 at 09:45h for now
|
|
|
|
|
|
|
|
|
**Sprint Backlog** : The team agreed that it should be reasonable to try to complete the following:
|
|
|
|
|
|
| **Priority** | **Story** | **Points** |
|
|
|
| ------------ | --------- | ---------- |
|
|
|
| 1 | #79 Counter/CounterBase | 13 |
|
|
|
| 2 | #95 ID31/15 Gasrig | 3 |
|
|
|
| 2 | #137 det_mca_core_for_Mercury | 1 |
|
|
|
| 2 | #134 contscan_id11_basic | 3 |
|
|
|
| 2 | #105 kb_focus | 5 |
|
|
|
| 2 | #110 motor_airpad | 3 |
|
|
|
| 2 | #131 motor_elmo_eth | 1 |
|
|
|
| 2 | #109 det_basler_bpm | 3 |
|
|
|
| 2 | #117 det_srcur | 3 |
|
|
|
| 2 | #112 motor_ice_linked_axis | 5 |
|
|
|
| 2 | #120 motor_ice_mux | 3 |
|
|
|
| 2 | TBC MCA_Core Story | around 13 |
|
|
|
| | **Total** | **around 54** |
|
|
|
|
|
|
![image](/uploads/6bc11fb93915d7f5f3adcb5ff465d050/image.png)
|
|
|
|
|
|
Also, Emmanuel confirmed that the original list of backlog items that he provided is correct and what the team should focus on for the rest of the year.
|
|
|
|
|
|
The Sprint Planning meeting was shorter than expected as task breakdowns will be prepared separately, rather than with the whole team. |
|
|