The 1st Sprint Planning meeting took place 28/08/2017 at 09:45 as planned.
|
|
|
|
|
|
List of attendees:
|
|
|
S. Petitdemange -> available during the sprint except 01/09 at 50%: 4.5 days
|
|
|
T. coutinho -> absent for two weeks
|
|
|
C. Guilloud -> absent 28/09 and 29/09 |
|
|
\ No newline at end of file |
|
|
Length of the sprint: 2 weeks (28/08 to 08/09)
|
|
|
|
|
|
| List of attendees | Availability | Total |
|
|
|
| --------------------- | -------------------------------------------------------------------------- | --------- |
|
|
|
| S. Petitdemange | available during the sprint except 01/09 at 50% | 4.5 days |
|
|
|
| T. coutinho | absent for two weeks | 0 days |
|
|
|
| C. Guilloud | absent 28/09 and 29/09 at 50% | 4days |
|
|
|
| V. Michel | available during the sprint except 01/09, 04/09 and 05/09 at 80% | 5.5 days |
|
|
|
| M. Guijarro | available excep 01/09 at 60% | 5 days |
|
|
|
| E. Papillon | absent (off-sick on the day) . Product Owner role | |
|
|
|
| J. Bodera | available (reduced availability Friday 08/09). Scrum Master role | |
|
|
|
|Total | | 19 days |
|
|
|
|
|
|
Unfortunately our Product Owner (PO), Emmanuel Papillon was off-sick, so the meeting went ahead without his help.
|
|
|
|
|
|
Daily Scrum to take place at 09:45 every day. Scheduled to last up to 15min, room booked for 30min just in case
|
|
|
Sprint Demo: Friday 08/09 at 13:00h
|
|
|
Sprint Retrospective: Friday 08/09 after the demo (14:00h)
|
|
|
Next Sprint planning scheduled for Monday 11/09 at 09:45h for now
|
|
|
|
|
|
The team agreed that it should be reasonable to try to complete the following:
|
|
|
1. #105 KB_focus
|
|
|
2. #137 det_mca_core_for_Mercury (we edited a story based on E. Papillon list to create this one)
|
|
|
3. #109 det_basler_bpm
|
|
|
4. #113 motor_ice_shutter
|
|
|
5. #114 beamviewer
|
|
|
6. #116 transfoc_lenses
|
|
|
|
|
|
As part of this exercise we agreed a "definition of done" and a task breakdown, like can be seen in the image:
|
|
|
![image](/uploads/d078168e48115f37a56aea6c2b82786d/image.png)
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Also, J. Bodera added a special item #138 Improve Product Backlog for E. Papillon, so we can have a more refined Product Backlog ahead of the next sprint.
|
|
|
|
|
|
Off-sprint, but noted:
|
|
|
1. J. Bodera added another item: #139 , which will need to be done at some point in the future.
|
|
|
2. J. Bodera will book a meeting for 06/09 or 07/09 to estimate items from the Product Backlog, so the next sprint planning meeting will be more fluid. This session will last up to 1 1/2h.
|
|
|
|
|
|
And that was it, we finished slightly earlier than planned (probably because we were fewer people than expected). |
|
|