The 1st Sprint Planning meeting took place 28/08/2017 at 09:45 as planned.
|
|
|
|
|
|
Length of the sprint: 2 weeks (28/08 to 08/09)
|
|
|
**Length of the sprint**: 2 weeks (28/08 to 08/09)
|
|
|
|
|
|
| List of attendees | Availability | Total |
|
|
|
| **List of attendees** | Availability | Total |
|
|
|
| --------------------- | -------------------------------------------------------------------------- | --------- |
|
|
|
| S. Petitdemange | available during the sprint except 01/09 at 50% | 4.5 days |
|
|
|
| T. coutinho | absent for two weeks | 0 days |
|
... | ... | @@ -15,10 +15,10 @@ Length of the sprint: 2 weeks (28/08 to 08/09) |
|
|
|
|
|
Unfortunately our Product Owner (PO), Emmanuel Papillon was off-sick, so the meeting went ahead without his help.
|
|
|
|
|
|
Daily Scrum to take place at 09:45 every day. Scheduled to last up to 15min, room booked for 30min just in case
|
|
|
Sprint Demo: Friday 08/09 at 13:00h
|
|
|
Sprint Retrospective: Friday 08/09 after the demo (14:00h)
|
|
|
Next Sprint planning scheduled for Monday 11/09 at 09:45h for now
|
|
|
**Daily Scrum** to take place at 09:45 every day. Scheduled to last up to 15min, room booked for 30min just in case
|
|
|
**Sprint Demo** : Friday 08/09 at 13:00h
|
|
|
**Sprint Retrospective**: Friday 08/09 after the demo (14:00h)
|
|
|
**Next Sprint planning** scheduled for Monday 11/09 at 09:45h for now
|
|
|
|
|
|
The team agreed that it should be reasonable to try to complete the following:
|
|
|
1. #105 KB_focus
|
... | ... | |