4th Sprint Follow up
This is the current picture of the items in the sprint:
Priority | Story | Points | Completed |
---|---|---|---|
Continuation | #105 Kb Focus | 5 | |
Continuation | #156 (closed) P201 in scans | 13 | 01/12/2017 |
Continuation | #172 (closed) Refactoring data handling | 13 | |
#140 (closed) 1D Data handling | 8 | 23/11/2017 | |
#132 (closed) motor symhexa v1 | 3 | ||
#133 (closed) motor pi e712 | 5 | ||
#165 (closed) Data file not always closed | 2 | 29/11/2017 | |
#173 (closed) MCA: further design specs | 5 | 30/11/2017 | |
#175 (closed) Discussion about "session" | 3 | 30/11/2017 | |
#174 hardware init discussion | 3 | ||
#177 (closed) Scan info dictionary & watch session scans | 3 | ||
U 21/11/2017 | #180 (closed) Banner when BLISS starts | 1 | 28/11/2017 |
U 22/11/2017 | #181 (closed) 'Pip install' doesn't work | 2 | 24/11/2017 |
U 28/11/2017 | #182 (closed) Improve musst controller | 1 | 28/11/2017 |
U 30/11/2017 | #183 (closed) No subdirectories allowed in motor scans | 1 | 30/11/2017 |
Planned Total | 63 | 31 | |
Unplanned Total | 5 | 5 | |
Grand Total | 68 | 36 |
These are the current burn down charts:
This is a rough estimation of the time spent on non-BLISS items:
Team Member | week 1 | week 2 | week 3 | Average |
---|---|---|---|---|
S. Petitdemange | 30% | 20% | ??% | 25% estimated |
T. coutinho | 90% | 30% | 40% | 60% |
C. Guilloud | 50% | 50% | 60% | 50% |
V. Michel | 40% | 10% | -------- | 25% |
M. Guijarro | 20% | 20% | 30% | 20% |
E. Papillon | 80% | 70% | 80% | 75% |
Total non-BLISS | 310% FTE | 200% FTE | 210% FTE | 42.5% |
As usual, we have a slow start (no points achieved during the first week) and by the end of the 2nd week the team agreed that we won't manage to complete everything in the sprint.
Towards the end of the sprint we realised that the number of planned points for the sprint wasn't 58 but 63 (somehow we missed adding 5 points!) and the burn down charts were redrawn.