... | ... | @@ -16,7 +16,7 @@ The 2nd Sprint Planning meeting took place 11/09/2017 at 09:45 as planned. |
|
|
| J. Bodera | Scrum Master role | 2 days |
|
|
|
|Total | | **47 days** |
|
|
|
|
|
|
So approximately we estimated that we will have around 47 days of available time for this sprint.
|
|
|
So we estimated that we will have around 47 days of available development time for this sprint.
|
|
|
|
|
|
|
|
|
Events:
|
... | ... | @@ -48,4 +48,9 @@ Events: |
|
|
|
|
|
Also, Emmanuel confirmed that the original list of backlog items that he provided is correct and what the team should focus on for the rest of the year.
|
|
|
|
|
|
The Sprint Planning meeting was shorter than expected as task breakdowns will be prepared separately, rather than with the whole team. |
|
|
\ No newline at end of file |
|
|
Changes in the Sprint
|
|
|
1. The Sprint Planning meeting was shorter than expected as task breakdowns will be prepared separately, rather than with the whole team present. We will monitor whether this change proves positive and streamlines the Sprint Planning meeting without adversely affecting the sprint.
|
|
|
2. We implemented a 3 week sprint (up from 2 weeks long) as recommended during the Sprint Retrospective
|
|
|
3. We changed the requirement for a Demo for each story to a Validation
|
|
|
4. No estimation meeting will take place this sprint (we quickly estimated some items during the sprint planning).
|
|
|
|