Closed
Milestone
Oct 31, 2018–Nov 27, 2018
MDT 27 November 8.00-10.00
MDT preliminary Plan: NO INJECTION POSSIBLE. 180mA from USM.
-
correct with BestCor option
-
minimize correctors with absolute COD correction (test OrbitCorrection)
-
matlab RM after beam accumulation from first turns continue correction: orbit correction, tune correction, optimal tune WP search, qem/sempanel, chromaticity correction, ...
take many screenshots.
FUTURE MDT's of if there is time.
-
tune from first turns (tunes for operation lattice and theory lattice, correction based on this values?)
-
bad initial condition (few BPMs see signal) (large radiation)
-
re-test on SY
-
K3/K4, bump amplitude, setting with InjBumpClosure
-
first turn with aperture limitations
-
tune scan after beam accumulation